White paper: It’s not just atoms that need bringing together in UK Fusion.

Written by
Priya Flora
|
October 23, 2026
|
10
Hinkley Point C showed what happens when a supply chain has to be rebuilt from scratch. STEP faces a similar challenge, and the time to act on it is before Tranche 2a scales up.

STEP has the physics, the funding and the site. What it hasn't yet solved is the one problem Hinkley Point C already got wrong in public: onboarding hundreds of unfamiliar suppliers before that becomes the bottleneck. In March 2026, the government published a new Fusion Strategy and named the ILIOS consortium as construction partner; by June, UK Fusion Energy (UKFE) had taken control of the site. The programme is no longer research; it's delivery, backed by £1.3bn of the government's £2.5bn fusion R&D commitment earmarked specifically for STEP.

STEP's biggest technical uncertainties sit with plasma physics and materials science, worked on by people who've spent careers on exactly this problem. Its biggest delivery uncertainty sits somewhere far less glamorous: whether the hundreds of supply chain organisations STEP will need, most with no prior nuclear or fusion experience, can be brought into a single, compliant information environment fast enough to avoid becoming the bottleneck.  

That's not hypothetical. It's the risk that has already played out, in public, at Hinkley Point C, and Sizewell C's delivery partner is now explicitly building its supply chain strategy around not repeating that mistake.‍

Different technology, different regulator  

Fusion combines rather than splits atoms, so the reaction can't run away the way a fission chain reaction theoretically can, and there's none of the long-lived high-level waste that comes with spent fission fuel.  

The hard part has always been containing plasma, a superheated charged gas, long enough and densely enough to get more energy out than was put in. STEP takes a spherical tokamak approach rather than the conventional doughnut shape used by ITER in France: a tighter, higher-pressure design that, building on results from the MAST Upgrade experiment at Culham, aims to reach net energy on a cheaper, faster timeline than a larger conventional machine.

That distinct design comes with a distinct regulatory status. The Energy Act 2023 excludes fusion facilities from the fission site-licensing regime entirely, making the UK the first country to formally regulate fusion separately, with the Environment Agency and HSE overseeing fusion plants rather than the Office for Nuclear Regulation, which regulates nuclear fission plants.

That's good news for delivery speed, but it also means STEP cannot simply inherit fission's existing supplier base.

A contractor's nuclear credentials from Hinkley or Sizewell don't automatically translate into fusion-specific competency, and every organisation, including a large share of SMEs with no nuclear or fusion exposure at all, must be assessed and onboarded into STEP's information environment on STEP's terms.  

Programme status and the scale of the supply chain

West Burton, a former coal-fired station near Gainsborough, is the chosen site: an 800-acre retiring fossil fuel plant with existing grid connections and an established energy workforce. UKFE (formerly UK Industrial Fusion Solutions, renamed as part of the March 2026 Fusion Strategy) now sits within the wider UKAEA family, running a tiered partner structure:  

  • UKAEA as Fusion Partner
  • ILIOS as Construction Partner under a first-tranche £200m contract
  • A pipeline of Engineering Partners yet to be confirmed
  • System Partners including Tokamak Energy for HTS magnets

By June 2026, UKFE had taken formal control of the West Burton site, with demolition, ash extraction and enabling works under way; the programme has now entered Tranche 2a, a four-year phase UKFE itself describes as where "the real scale-up begins."  

Supply chain engagement is already substantial for a programme still in its enabling phase. UKFE's own strategy document records 854 supplier organisations engaged between April 2019 and February 2026, around 84% UK-based, including 521 SMEs and 49 local suppliers around West Burton itself, a 74% increase in local numbers since 2023. Industry spend to date stands at £125.5m, of which £103.1m has gone to UK-based organisations.  

In July 2026, UKFE ran a two-day "Meet the Buyer" event in Worksop, drawing hundreds of prospective suppliers alongside ILIOS, Tokamak Energy, Dassault Systèmes and UKAEA. STEP is also the anchor project for the Trent Clean Energy Supercluster, the regional growth initiative led by the East Midlands Combined County Authority spanning the East Midlands, Lincolnshire and South Yorkshire.  

The government puts job creation from the programme and the wider fusion sector at over 10,000 by 2030.

Policy, investment and the scale of the ambition  

Government's March 2026 Fusion Strategy builds on a £2.5bn five-year R&D commitment, of which £1.3bn is earmarked specifically for STEP, structured around three aims: accelerating R&D, growing industry, and building the market and regulatory conditions fusion needs to attract private capital.

Skills are a priority: £50m is committed specifically to fusion skills development, targeting more than 2,000 people trained from apprenticeships to postdoctoral research, alongside a Diagnostics Centre for Excellence (DICE) and a dedicated robotics skills centre in Cumbria (CROSS) for the remote-handling workforce fusion will need.

A draft National Policy Statement for Fusion (EN-8) was published in summer 2026 to simplify planning for fusion developments, alongside an investment prospectus and direct capitalisation support from the British Business Bank and National Wealth Fund.  

UKFE's own strategy frames the prize in striking terms: a global fusion industrial opportunity it values at £3–12 trillion by the end of the century, with the UK positioning itself, as the first country with both a published fusion strategy and a dedicated fusion regulatory framework, to lead rather than simply participate.

A cautionary tale in public view

Hinkley Point C offers an instructive lesson. At its 2016 final investment decision, the project was costed at £18bn with completion targeted for 2025. The most recent public guidance now points to operations starting in 2030 and a total cost around £35bn at 2015 prices. Some 2026 assessments are more pessimistic, running as high as £46bn once inflation to current prices is included, alongside a further €2.5bn impairment charge EDF announced in February 2026.

Hinkley's own site leadership has been candid about the cause: a twenty-year pause in UK nuclear construction meant the programme had to rebuild capability that no longer existed, relearn nuclear skills, stand up a new supply chain, and train a workforce essentially from scratch. Industry commentary has drawn a direct line from that capability gap to the scale of the overrun, alongside genuine external shocks like the pandemic, Brexit and materials inflation.

The lesson is being acted on, not just noted: Sizewell C's delivery partner has stated explicitly that transferring supply chain management capability and lessons learned from Hinkley was one of its first tasks. And STEP has an advantage neither Hinkley nor early Sizewell had: the lesson has already been written down, in public, by the people who lived through it.  

The question is whether it will be applied to STEP's own supply chain (hundreds of Tier 2/3 organisations) before onboarding becomes the bottleneck, or after.

The £30m platform is ready. Are the users?

ISO 19650 exists precisely because large, multi-party programmes were losing time, money and quality to the kind of fragmented information handling that now threatens STEP's supply chain onboarding.

At its centre is the Common Data Environment: a single, agreed source of project information, with role-based access controls and data organised through defined states, so everyone involved in the programme works from the same, current, audited version of the truth. A widely cited industry figure puts what's at stake starkly: an estimated 96% of engineering and construction data generated on projects is never meaningfully exploited.

STEP has already invested seriously here. In 2026, UKFE signed a £30m contract with Dassault Systèmes to expand its 3DEXPERIENCE platform into the trusted environment intended to hold design data, requirements, simulations and system models across the whole engineering lifecycle, explicitly described as the foundation for STEP's future digital shadows and twins of the plant.  

But building a platform is not the same as being ready to use it.

The real question is whether the hundreds of supply chain organisations STEP needs are actually equipped, trained and assessed to use that environment correctly from day one or whether its value gets eroded by the same inconsistent onboarding, naming conventions and data exchange practices BIM and ISO 19650 were designed to eliminate in the first place.

Why this is urgent now, not later

Supply chain readiness is far cheaper to build before a programme scales than to repair afterwards. Three things make that true for STEP: its scale, its timing, and the consequence of getting it wrong.

Scale

UKFE's own figures put engaged suppliers at 854 as of February 2026, while the programme is still in its enabling phase. Hinkley Point C has around 2,500 contracted supply chain organisations at full build, meaning STEP is already roughly a third of the way to a comparable nuclear-scale programme before Tranche 2a's scale-up has properly begun. At Hinkley-equivalent scale, individual-user onboarding runs into the tens of thousands, not the hundreds a conventional project team is set up to manage informally.

Timing

Readiness needs to be evidenced before an organisation is provisioned into STEP's Common Data Platform and PIMS environment, not discovered afterwards through failed data exchanges or missed information requirements. Retrofitting compliance after data has already started flowing is always slower and more expensive than establishing it up front, and the digital construction sector already has documented examples of the costly remediation that follows non-compliant information exchange.

Consequence

STEP faces a comparable structural challenge to Hinkley's, arguably harder, since it can't even fully inherit fission's existing supplier base, at a stage where the cost of getting readiness wrong is still largely avoidable rather than already banked into a public overrun.  

None of this puts STEP's engineering leadership into question: its £30m platform investment and 854 engaged suppliers show a programme that understands the scale of what's coming. The argument is narrower: the interface between "willing, engaged supplier" and "compliant, competent, provisioned participant" doesn't manage itself at this scale.  

Treating it as an extension of core engineering delivery, rather than its own discipline with its own tools and process, is precisely the pattern that inflated Hinkley's cost and schedule.

Majenta's role

Majenta has spent 30 years working at the point where large, complex programmes meet the organisations that have to deliver them, building the discipline and systems that move supply chains from interested to onboarded, compliant and productive across construction, infrastructure and other regulated sectors.  

That experience maps directly onto STEP's challenge: bringing a large, unfamiliar supply chain into a first-of-a-kind information environment, at pace, without compromising quality or compliance.

The lesson from Hinkley Point C is visible. Whether it gets applied to STEP is a question of timing, not possibility. What is clear is that the cost of answering it now, ahead of Tranche 2a's scale-up, is a fraction of the cost of answering it after the fact. ‍

This paper's recommendation is straightforward. STEP's information management leadership should treat supply chain readiness as a distinct workstream, with its own tools, standards and governance, rather than an informal extension of core engineering delivery, and should do so at the earliest opportunity.

Majenta would welcome the opportunity to set out what a fusion-specific readiness layer for STEP could look like, sitting alongside its core engineering systems rather than replacing them.

Key contact

Priya Flora, Partnership Manager, Majenta Solutions

Sources:  

FAQs - STEP Fusion

UK Fusion Energy Ltd Strategy - STEP Fusion

The Spherical Tokamak for Energy Production: theme issue introduction | Philosophical Transactions of the Royal Society A

UK developing regulatory framework for fusion - World Nuclear News

UK Industrial Fusion Solutions publishes first Annual Report

Hundreds of UK businesses attend our Meet the Buyer event - STEP Fusion

A new energy revolution: The UK's plan for delivering fusion energy (accessible webpage) - GOV.UK  

UKAEA unveils 2026-2030 fusion roadmap - Nuclear Industry Association

Fusion Strategy Volume 782: debated on Monday 16 March 2026 - Hansard

Draft National Policy Statement for fusion energy generation (EN-8) - GOV.UK  

Interview: Amentum on optimism for Sizewell C and role in the nuclear fuel supply chain | New Civil Engineer

Hinkley Point C Report - National Audit Office

EDF announces Hinkley Point C delay and rise in project cost - World Nuclear News

Delays Hit U.K.'s Hinkley Point C Nuclear Project Again

Relearning how to build nuclear in the U.K.

UK Fusion Energy signs £30m contract to expand STEP Fusion digital platform

Guide to the Common Data Environment (CDE) & BIM | Procore‍