White paper: Building Britain's energy backbone

Two global energy shocks in under four years: the 2022 gas crisis after Russia's invasion of Ukraine, and renewed Middle East volatility in 2025–26, have shown how exposed Britain remains to fuels whose price or supply it doesn't control. This paper sets out the scale of the problem, where the gaps are, and how to close them.
A world re-securing its energy
The IEA describes the current period as the second major global energy supply shock in five years, reinforcing a shift towards security, trust and diversity.
Nations are responding the same way everywhere: prioritising domestic and regional capacity over exposure to volatile international markets. Global energy investment is projected to reach US$3.4 trillion in 2026, and for the first time electricity accounts for close to 60% of it, overtaking oil and gas. Spending on grids specifically is set to approach $550bn in 2026.
The IEA's modelling is blunt about what that entails:
- Global electricity demand is forecast to grow 3.6% a year to 2030, roughly 50% faster than the last decade
- Annual global grid investment needs to rise by around 50% by 2030 from a 2025 baseline of roughly $400bn
Grids, not generation, are now the binding constraint: planning, consenting and building new transmission typically takes five to fifteen years, several times longer than the wind farms, solar arrays and data centres it exists to connect.
More than 2,500 GW of renewable, storage and large-load projects are currently stalled worldwide, waiting for grid capacity that doesn't exist yet.
How exposed is the UK energy sector?
Britain illustrates the global pattern with unusual clarity. UK domestic energy production has fallen 68% from its 1999 peak as North Sea reserves deplete, and net import dependency stood at 43.3% in 2025.
Without the wind, solar and hydro generated on British soil in 2025, an estimated 73% of the primary energy used to supply UK electricity would have had to be imported, overwhelmingly as gas. Instead, renewables supplied 52.5% of the UK's electricity – setting a new record in the process.
Key figures at a glance
- UK net energy import dependency: 43.3%
- Decline in UK domestic energy production since 1999 peak: 68%
- Share of UK electricity primary energy that would be imported without domestic renewables: 73%
- Share of UK gas supply that is imported: ~45%
- Renewable share of UK electricity generation: 52.5%
Gas remains the principal exposure. Around 45% of UK gas supply is imported, and gas sets the wholesale electricity price in most settlement periods, so a single LNG cargo can still set what the whole country pays even when renewables are generating cheaply. The government's own position, through the Department for Energy Security and Net Zero, is that the way out isn't a return to domestic fossil fuel production, which is structurally in decline regardless of policy, but electrification: converting demand for imported fuel into demand for electricity Britain can generate, transmit and control itself.
That requires a transmission network able to carry enough home-grown clean power to where it's needed, at a pace and scale the network has never attempted.
The money for that build is now largely approved. What isn't yet solved is delivery: enough people who can plan, design, coordinate and construct complex electrical infrastructure fast enough, and enough digital discipline to stop that scarce capacity being wasted on rework and miscoordination.
Clean Power 2030 and the grid build-out
Clean Power 2030 targets at least 95% low-carbon generation by 2030, requiring 43–50 GW of offshore wind, 27–29 GW of onshore wind and 45–47 GW of solar, according to the current Action Plan.
None of that capacity is worth anything without a transmission network able to carry it from where it's generated, largely offshore and in Scotland, to where it's consumed. That's the direct origin of the current investment programme.
Ofgem's RIIO-3 Final Determination (December 2025) approved £28.1bn of upfront investment across electricity and gas transmission and gas distribution for 2026–31, inside a wider £90bn pipeline. National Grid Electricity Transmission's own plan separately runs to £35bn, including the first tranche of Accelerated Strategic Transmission Investment (ASTI) projects, a fast-track mechanism Ofgem created because conventional timescales couldn't keep pace with 2030 targets. ASTI itself covers 26 projects worth a combined £20bn.
On 12 May 2026, Ofgem completed Early Construction Funding decisions on the remaining Scottish ASTI projects. All 26 ASTI projects now have early funding in place, letting Transmission Owners commit finance to procurement, land and design work ahead of full consent, though it doesn't remove the planning and consenting step itself, which is still the slower-moving constraint.
Separately, the connections queue reform matters just as much. By late 2024, more than 738 GW of proposed projects were waiting for a grid connection offer, over three times the capacity actually needed for 2030 targets, with some developers facing indicative dates in the late 2030s. NESO's reform, replacing first-come-first-served with "first ready, first needed, first connected," confirmed its new pipeline in December 2025, and NESO says the reform could unlock £40bn of investment a year.
Where the gap is actually located
The UK energy sector is estimated to need around 400,000 additional roles by 2050 to meet net-zero commitments.
Morson Group's 2026 sector report names acute shortages across nuclear, power engineering, grid infrastructure, construction management, commissioning and operations as the single biggest delivery risk to the entire programme, greater than either capital availability or political intent.
Prospect union's 2023 survey of 2,000 energy network workers found 69% of transmission and distribution staff reporting skills shortages or gaps in their own organisation, with a lack of experienced engineers the most common concern. Four out of five respondents described staffing levels as “too low” in their workplaces.
Nuclear new-build, offshore wind, the grid upgrade and carbon capture clusters are all mobilising in parallel, competing for the same welders, fitters and engineers, and the ASTI mechanism compresses the delivery window further, leaving project teams less time to mobilise robust digital and information management processes than a conventional programme would allow. The funding has, in large part, now been approved. The bottleneck has shifted to delivery capability.
This is the exact pattern Majenta has already seen play out in the water sector's AMP8 programme, another well-funded, clearly mandated investment constrained less by money than by the availability of skilled, experienced people.
Why digital construction is now a delivery necessity
All three Transmission Owners now mandate BIM compliance and increasingly specify 4D planning as a delivery requirement, not a discretionary extra.
McKinsey Global Institute estimates that closing construction's long-standing productivity gap against the wider economy would add $1.6 trillion in value globally, a gap caused largely by fragmented workflows, rework and poor information flow.
The evidence isn't only generic to construction; it holds up specifically in transmission.
- A 2025 peer-reviewed study of 164 power substation projects delivered by China's State Grid, comparing 85 built with BIM against 79 without, found BIM didn't necessarily lower total project costs, but made them significantly more predictable: the variance between budgeted and final settlement costs became measurably tighter on BIM-enabled projects.
- On India's NER-II transmission project, an integrated 3D and 4D BIM and digital twin workflow identified electrical clearance issues and clashes early enough to avoid rework, saving the project over a month on schedule and delivering a 15% return on investment through real-time virtual construction monitoring.
This is already visible on live projects in the UK too. On the Sellafield Product and Residue Store Retreatment Plant, a nuclear facility at Europe's largest nuclear site, the client mandated 4D modelling of the mechanical and electrical works, and Majenta was the only respondent able to demonstrate the combination of 4D expertise and nuclear-sector clearance the project required. Embedded within contractor Balfour Beatty Kilpatrick's team, that work has identified over 2,000 issues across the project's electrical, control and instrumentation and pipework packages, resolved in the model rather than discovered, at far greater cost, on site.
The same pattern is now emerging directly within transmission: SSEN Transmission has begun piloting 4D planning on its own projects, and, in the words of Majenta's Senior Information & 4D Manager, Lyle Murphy:
"4D is going to be absolutely crucial for ASTI. Clients have recognised it. They've prescribed the use of 4D on all projects within the framework."
This isn't only a Majenta observation. IM4Power, the cross-industry information management body founded in late 2024 by National Grid, SP Transmission and SSEN Transmission alongside supply chain partners including Hitachi Energy, Siemens and Balfour Beatty, and deliberately modelled on the water sector's BIM4Water, runs its own 4D-focused workstream, aiming to “develop a standard framework for visualising the timeline of asset creation that the supply chain can use when delivering projects in the sector”.
Majenta's role in closing the gap
Majenta isn't approaching transmission from a standing start: the business already has direct relationships with the digital engineering teams inside all three Transmission Owners, and active commercial relationships with several Tier 1 delivery partners across the ASTI supply chain.
As RIIO-T3 and ASTI move from planning to delivery over the next five years, the organisations that succeed will be those which treat digital engineering as infrastructure in its own right, not an afterthought bolted on once a project is already under pressure.
The grid can't be built faster by approving more money; it can only be built faster by finding more of the specific people needed to construct it and by making the people already on the programme significantly more productive.
Talk to Majenta about adding flexible digital delivery capacity to your ASTI or RIIO-T3 projects now, while procurement is already under way, so the capability is ready the moment consent is granted, not when the shortage is already being felt.
Key contact
Priya Flora, Partnership Manager, Majenta Solutions
Sources:
World Energy Investment 2026 – Analysis - IEA
Energy Trends: UK total energy - GOV.UK
Energy & Climate Intelligence Unit | UK electricity defies North Sea decline
UK electricity defies North Sea decline in two-decade homegrown high - Scottish Business News
Clean Power 2030 Action Plan: A new era of clean electricity – technical annex - GOV.UK
Clean Power 2030 Action Plan: A new era of clean electricity - GOV.UK
National Grid Electricity Transmission
Connections Reform | National Energy System Operator
Your concerns from the frontline of the energy sector | Prospect
Reinventing construction through a productivity revolution | McKinsey
Impact Analysis of BIM on Power Substation Project Costs: Techno-Economic Data Evidence from China
Case Study: Sterlite Power delivers light to India’s most remote regions using renewable energy