Community consent is now a delivery risk, not a PR problem

Written by
Sam Lissaman
|
November 23, 2026
|
3
Thousands of objections and a string of public inquiries are slowing Britain's grid upgrade. We look at why community consent is now a programme risk, and how clear 4D visualisation helped one project avoid weeks of delay.

More than 10,400 objections were lodged ahead of a public inquiry into a single Scottish pylon scheme, one of the highest volumes of objections ever recorded against a UK overhead line project. It's not an isolated case. We've seen a confirmed public inquiry into SSEN Transmission's 170km Spittal to Beauly line in the Highlands; formal objections from Babergh, Mid Suffolk and Brentwood councils to National Grid's 184km Norwich to Tilbury route and a long-running campaign against SP Energy Networks' line through Dumfries and Galloway.  

It would be easy to read all of this as a communications challenge, a PR problem to be managed with better leaflets and more open days. That's a mistake. On a programme where Ofgem has explicitly designed the ASTI mechanism to compress delivery timescales that would otherwise miss 2030 targets, a public inquiry can cost vital time as well as generating headlines.

How do public inquiries delay construction programmes?

Spittal to Beauly's inquiry process alone will run for months, with reporters appointed, hearing sessions scheduled, and a final decision that may still be appealed. Multiply that pattern across the 26 ASTI projects Ofgem has identified, or the wider pipeline of RIIO-T3 reinforcement schemes, and the cumulative delay risk to Britain's 2030 clean power target becomes serious: not a handful of unlucky projects, but a structural brake on the entire programme.  

Our white paper, Building Britain's Energy Backbone, sets this out at a system level: the International Energy Agency's own analysis finds that planning, consenting and constructing new transmission infrastructure typically takes five to fifteen years globally, several times longer than it takes to build the generation and demand-side assets, like offshore wind farms or data centres, that the grid exists to connect. Every year added to grid-side consenting widens that gap further.

How can public objections to construction be reduced?

There's no way to make a 50-metre pylon disappear, and no visualisation tool will turn every objector into a supporter. But the evidence from Majenta's own work in the water sector is instructive.  

On a live sewer upgrade project for Scottish Water, using 4D visualisation to support public consultation and address planning objections is estimated to have avoided around four weeks of planning delay, not by hiding the disruption, but by making it precise, bounded and honestly explained, rather than left to imagination.  

The same principle applies directly to transmission routes running through sensitive landscapes. A community that can see exactly which fields will be affected, for how long, and in what sequence, is dealing with a specific, time-limited disruption. A community working from a static route map and a stack of technical documents is often, understandably, imagining the worst version of an open-ended one.

An important caveat

It's worth being clear: we're not suggesting that 4D visualisation is a substitute for genuine engagement, fair compensation, or credible route alternatives where they exist. Communities in Caithness, Suffolk and Dumfries and Galloway have raised real concerns about landscape, health impacts and property value that deserve serious answers, not just better graphics.  

But what visualisation and 4D planning can do is make sure that when those serious conversations happen, they're grounded in a precise, current, easily updated picture of what's actually being proposed, rather than adding confusion and mistrust on top of an already difficult conversation.

Facing consultation or public inquiry risk on a live scheme?

If you have a planned or current project at risk from delays related to a public consultation, speak to Majenta. Our Utilities Lead, Sam Lissaman, will be happy to talk through your project and answer questions about where 4D visualisation and planning could be deployed to improve stakeholder engagement and understanding, and reduce schedule risk.  

‍